04-10-26
In this report, the apparatus completed final assembly
and released to test. When testing completes it will
release to quality and graphics where any remaining
content will be applied. Once finished it will be made
ready for the customer acceptance inspection.
03-13-26
In this report, the pump house and the body were merged with the chassis at the start of initial apparatus assembly.
In this report, the cab was merged with the frame, the pump house continued initial assembly, and the body completed initial assembly.
02-27-26
In this report, the cab remained staged, the pump house continued initial assembly, and the body was staged.
02-20-26
In this report, the cab completed initial assembly, the pump house began initial assembly, and the body completed paint.
02-13-26
In this report, the cab continued initial assembly, the pump house structure remained staged, and the body began the paint process.
02-06-26
In this report, the cab began initial assembly, the pump house structure was staged, and the body completed fabrication.
01-30-26
In this report, the cab completed the paint process, the pump house structure began fabrication, and the body began fabrication.
12-19-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.