06-19-26
In this report, the apparatus was staged to complete test.
When testing completes it will release to quality and
graphics where any remaining content will be applied.
When finished it will be made ready for the customer
acceptance inspection. This is the last scheduled report.
06-12-26
In this report, the aerial device completed initial assembly
and was pinned to the apparatus followed by the start of
aerial testing.
06-05-26
In this report the body was merged with the chassis
and the apparatus completed final assembly while
the aerial device arrived and began initial assembly.
05-22-26
In this report, the torque box was merged with the chassis while the tank and body were in queue to be mounted.
05-15-26
In this report, the pump house was merged with the
chassis, the torque box began initial assembly, and
the body completed initial assembly.
05-08-26
In this report your cab was merged with the frame while
assembly continued, the pump house completed initial
assembly, the torque box arrived and was staged, and the
body remained staged.
05-01-26
In this report, the cab was staged, the frame build began, the pump house continued initial assembly, and the body completed the paint process.
04-24-26
In this report, the cab completed initial assembly, the pump house was staged to continue initial assembly, and the body continued through paint.
04-17-26
In this report, the cab began initial assembly, the pump house was painted then staged to continue initial assembly, and the body completed fabrication and began the paint process.
04-10-26
In this report, the cab was staged to begin initial assembly, the pump house began initial assembly, and the body began fabrication.
02-27-26
This new Pierce apparatus is now in production! In this report, the cab began fabrication.