06-05-26
In this report, the apparatus completed testing followed by release to quality and graphics where any remaining content will be applied. Once finished it will be made ready for the customer acceptance inspection. This is the last scheduled report.
05-22-26
In this report, the aerial device completed initial assembly
and was pinned to the apparatus followed by the start of
aerial testing.
05-15-26
In this report, the turntable module and the body were
merged with the chassis then the apparatus began final
assembly.
05-08-26
In this report, the chassis assembly continued, the turntable
module was in queue for initial assembly, and the body was staged to be mounted.
05-01-26
In this report, the torque box was being installed on the chassis, the turntable module was staged, and the body remained unavailable for photos.
04-24-26
In this report, the cab and pump were merged with the frame, the torque box began initial assembly, the turntable module completed paint, and the body was unavailable for photos.
04-17-26
In this report, the cab was staged, the frame build continued, the pump house was in queue for installation, the torque box arrived and was staged, the turntable module was unavailable, and the body was staged.
04-10-26
In this report, the cab completed initial assembly, the frame build continued, the pump house was staged, the turntable module began fabrication, and the body completed the paint process.
04-03-26
In this report, the cab began initial assembly, the pump house completed initial assembly, and the body was unavailable for photos.
03-20-26
In this report, the cab remained staged, the pump house structure was fabricated and painted, and the body began fabrication.
02-06-26
This new Pierce apparatus is now in production! In this report, the cab began fabrication.