05-22-26
In this report, the apparatus completed final assembly
and began test. When testing completes it will release
to final product evaluation where any remaining content will be applied.
05-01-26
In this report, the cab and pump house were merged with the frame followed by body installation at the start of initial apparatus assembly.
04-24-26
In this report, the cab continued initial assembly, the frame build continued, the pump house was staged, and the body completed initial assembly.
04-17-26
In this report, the cab began initial assembly, the frame build continued, the pump house completed initial assembly, and the body began initial assembly.
04-10-26
In this report, the cab and frame remained staged (no photos), the pump house was painted then continued initial assembly, and the body was staged.
04-03-26
In this report, the cab was staged, the frame remained staged (no photos), the pump house began the paint process, and the body completed paint.
03-27-26
In this report, the cab completed paint, the frame was staged (no photos), the pump house was staged, and the body continued the paint process.
03-20-26
In this report, the cab began the paint process, the frame build arrived in Bradenton, the pump house continued initial assembly, and the body continued through paint.
03-13-26
In this report, the cab was staged (no photos), the pump house began initial assembly, and the body began the paint process.
03-06-26
In this report, the cab remained staged, the pump plumbing continued assembly, and the body completed fabrication.
02-27-26
In this report, the cab was staged, the pump plumbing began assembly, and the body continued the fabrication process.
02-20-26
In this report, the cab completed fabrication while the body continued the fabrication process.
02-13-26
This new Pierce apparatus is now in production! In this report, the cab began fabrication while the body panels began fabrication.