40656 – Toms River

Enforcer Pumper
Job #: 40656

PROGRESS UPDATES


10-09-26

In this report, the cab continued through paint, the
pump house continued initial assembly, and the
body was fabricated then staged.


10-02-26

In this report, the cab continued the paint process, the pump house began initial assembly,
and the body began fabrication.


09-25-26

In this report, the cab continued through paint while the pump house structure was fabricated.


09-19-26

In this report, the cab completed fabrication and began the paint process with metal finishing.


09-11-26

This new Pierce apparatus is now in production! In this report, the cab began fabrication.