09-18-26
In this report, the apparatus completed test and released to quality and graphics where any
remaining content is applied. Once finished it will be made ready for the customer acceptance
inspection. This is the last scheduled report.
08-21-26
In this report, the body was merged with the chassis at the start of initial apparatus assembly.
08-14-26
In this report, the cab and pump house were merged with
the frame while the body completed the paint process.
08-07-26
In this report your cab completed initial assembly, the frame build continued, the pump house was in
queue for installation, and the body was fabricated and began the paint process.
07-31-26
In this report, the cab continued initial assembly, the frame build continued, and the pump house completed initial assembly.
07-24-26
In this report, the cab completed the paint process and began initial assembly, the frame build continued, and the pump house continued initial assembly.
07-17-26
In this report, the cab continued through paint, the frame build continued, and the pump house began initial assembly.
07-10-26
In this report, the cab completed fabrication and began the paint process with metal finishing while the frame build began.
06-26-26
This new Pierce apparatus is now in production! In this report, the cab began fabrication.