39835 – Shamong/Indian Mills – Enforcer Pumper

Enforcer Pumper
Job #: 39835

PROGRESS UPDATES


02-20-26

In this report, the apparatus completed final assembly and released to test.


02-06-26

In this report, the body was merged with the chassis at the start of initial apparatus assembly.


01-30-26

In this report, the cab and pump house were merged with the frame while assembly continued, and the body began initial assembly.


01-23-26

In this report, the cab began initial assembly, the frame build continued (no photos), the pump house completed initial assembly, and the body completed paint.


01-16-26

In this report, the cab completed paint, the frame build continued (no photos), the pump house was painted then staged to continue initial assembly, and the body completed fabrication and began the paint process.


01-09-26

In this report, the cab continued through paint, the frame build began, the pump house began initial assembly, and the body began fabrication.


12-19-25

In this report, the cab was staged to continue through paint while the pump house structure was fabricated.


12-12-25

In this report, the cab completed fabrication and began the paint process.


12-05-25

In this report, the cab continued fabrication.


11-21-25

This Pierce apparatus is now in production! In this report, the cab began fabrication.