01-30-26
In this report, the apparatus continued through quality and graphics where any remaining
content will be applied. Once complete it will be made ready for the customer acceptance
inspection. This is the last scheduled report.
01-23-26
In this report, the apparatus completed final assembly and test followed by release to quality and graphics where any remaining content will be applied.
12-19-25
In this report, the body was merged with the chassis at the start of initial apparatus assembly.
12-05-25
In this report, the cab and pump house were merged with the frame while the body completed initial assembly.
11-14-25
In this report, the cab completed paint and began initial assembly, the pump house began initial assembly, and the body began fabrication.
11-07-25
In this report your cab began the paint process while the pump house structure was staged.
10-31-25
In this report, the cab completed fabrication while the pump house structure began fabrication.
10-24-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.