08-08-25
In this report, the apparatus completed testing followed by release to quality and graphics where any remaining content will be applied. Once finished, it will be made ready for the customer acceptance inspection. This is the last scheduled report.
07-18-25
In this report, the cab, pump house, and body were merged with the frame at the start of initial apparatus assembly.
07-11-25
In this report, the cab completed paint and began initial assembly, the frame build began, the pump house completed initial assembly, and the body began the paint process.
06-20-25
In this report, the cab continued the paint process, the pump house structure was fabricated, and the body began fabrication.
05-23-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.