41212 – Little Falls – Saber Pumper

Saber Pumper
Job #: 41212

PROGRESS UPDATES


01-09-26

In this report, the body was merged with the chassis followed by the start of final assembly.


12-19-25

In this report, the cab and pump house were merged with the frame while the body continued initial assembly.


12-12-25

In this report, the cab completed initial assembly, the frame build continued, the pump house continued initial assembly, and the body continued initial assembly.


12-05-25

In this report, the cab began initial assembly, the frame build continued, the pump house continued initial assembly, and the body began initial assembly.


11-14-25

In this report, the cab completed paint, the frame build began, the pump house remained staged, and the body remained staged (no photos).


11-07-25

In this report, the cab began the paint process, the pump house remained staged, and the body completed the paint process and was staged.


10-31-25

In this report, the cab and pump house remained staged while the body completed fabrication and began the paint process.


10-24-25

In this report, the cab remained staged (no photos), the pump house was painted, and the body continued fabrication.


10-17-25

In this report, the cab remained staged (no photos), the pump house began initial assembly, and the body continued the fabrication process.


10-10-25

In this report, the cab was fabricated and staged while the body continued the fabrication process.


10-03-25

This new Pierce apparatus is now in production! In this report, the body began fabrication.