10-10-25
In this report, the aerial device completed initial assembly and was pinned to the apparatus followed by the start of aerial testing.
10-03-25
In this report, the apparatus completed final assembly while the aerial device continued initial assembly.
09-26-25
In this report, the turntable module was installed as your apparatus completed initial assembly and began final assembly while the aerial device arrived and began initial assembly.
09-19-25
In this report, the torque box completed initial assembly and was merged with the chassis followed by the body completing paint and initial assembly then being installed while the turntable module was unavailable for photos.
09-12-25
In this report, the chassis was staged to continue assembly, the torque box arrived and was staged, the turntable module was fabricated and began the paint process, and the body began in paint.
09-05-25
In this report, the chassis was staged to continue assembly while the body was staged to begin the paint process.
08-22-25
In this report, the cab completed initial assembly and was merged with the frame, the pump house completed initial assembly and was queued to be mounted on the chassis, and the body completed fabrication and was staged.
08-15-25
In this report, the cab continued initial assembly, the frame build continued, the pump house structure was fabricated then painted, and the body began fabrication.
08-08-25
In this report, the cab completed paint and began initial assembly while the frame build began.
06-27-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.