08-08-25
In this report, the apparatus completed test and was released to final product evaluation where any remaining content will be applied. Once finished, it will be made ready for the customer acceptance inspection. This is the last scheduled report.
06-20-25
In this report, the pump house and tank were installed on the chassis while the body completed initial assembly.
06-13-25
In this report, the cab completed initial assembly and was merged with the frame, the pump house was staged (no photos), and the body began initial assembly.
06-06-25
In this report, the cab continued initial assembly, the frame build continued, the pump house completed testing, and the body remained staged (no photos).
05-30-25
In this report, the cab began initial assembly, the frame build continued, the pump house was staged for testing, and the body remained staged (no photos).
05-23-25
In this report, the cab, frame, and body were staged (no photos) while the pump house completed initial assembly.
05-16-25
In this report, the cab completed the paint process, the frame remained staged (no photos), the pump house was painted and continued initial assembly, and the body completed fabrication and paint.
05-02-25
In this report, the cab was staged, the frame was staged (no photos), the pump house continued initial assembly, and the body continued the fabrication process.
04-25-25
In this report, the cab was fabricated, the frame build began, the pump house continued initial assembly, and the body continued fabrication.
04-18-25
This new Pierce apparatus is now in production! In this report, the pump house began initial assembly while the body began fabrication.