01-30-26
In this report, the apparatus completed test followed
by release to quality and graphics where any remaining content will be applied. Once complete it will be made ready for the customer acceptance
inspection. This is the last scheduled report.
01-23-26
In this report, the apparatus completed final assembly followed by the aerial device being pinned and the start of aerial testing.
12-19-25
In this report, the forward PUC module and the body were merged with the chassis, and the apparatus began final assembly.
12-12-25
In this report, the torque box was installed on the chassis, the forward PUC module was staged, and the body completed initial assembly.
12-05-25
In this report, the cab was merged with the frame, the torque box began initial assembly, the forward PUC module completed paint and began plumbing installation, and the body began initial assembly.
11-14-25
In this report, the cab completed initial assembly, the frame build began, the forward PUC module began the paint process, and the body completed paint.
11-07-25
In this report, the cab continued initial assembly, the forward PUC module remained staged, and the body completed fabrication and began the paint process.
10-31-25
In this report, the cab completed paint and began initial assembly, the forward PUC module was fabricated and staged, and the body began fabrication.
10-03-25
This new Pierce apparatus is now in production! In this report, the cab began fabrication.