PROGRESS UPDATES


08-01-25

In this report, the apparatus completed final assembly and test then released to quality and graphics where any remaining content will be applied.


07-18-25

In this report, the body completed initial assembly and was installed on the chassis.


07-11-25

In this report, the cab and pump house completed initial assembly then were merged with the frame while the body began initial assembly.


06-20-25

In this report, the cab continued the paint process while the pump house began initial assembly.


06-13-25

In this report, the cab continued through paint while the pump house continued fabrication.


06-06-25

In this report, the cab completed fabrication and began the paint process with metal finishing while the pump house structure was fabricated.


05-30-25

This new Pierce apparatus is now in production! In this report, the cab began fabrication.