10-31-25
In this report, the cab, pump house, and body were merged with the frame at the start of initial apparatus assembly.
10-24-25
In this report, the cab completed paint and began initial assembly, the frame build continued, the pump house remained staged, and the body continued through paint.
10-17-25
In this report, the cab began the paint process, the frame build continued, the pump house completed initial assembly, and the body began the paint process.
10-10-25
In this report, the cab completed fabrication, the frame build continued, the pump house was painted then staged to continue initial assembly, and the body completed fabrication.
10-03-25
In this report, the cab began fabrication, the frame build began, the pump house began initial assembly, and the body began the fabrication process.
09-26-25
This new Pierce apparatus is now in production!
In this report, the pump house structure was fabricated.